The draft stage of the repair begins immediately after the signing of the contract with our company. In this article we will analyze what work is included in the draft stage and in what sequence.
Content
- Stage 1. Dismantling
- Stage 2. Installation of partitions
- Stage 3. Stucked
- Stage 4. Black electrician
- Stage 5. Black plumbing
- Stage 6.
- It is important to know
Stage 1. Dismantling
If redevelopment is conceived in the apartment, then the repair begins with the dismantling of partitions, doorways, radiators and other elements.
Photo: In the apartments of the old fund for dismantling, there is also plaster, floors, screed, electrician, ceilings and more.
Also at this stage, materials for repair are purchased. The client writes a power of attorney to pass, parking and provides it to the management company so that the foreman and builders always have access to the facility,
At the end of each stage, a specialist in technical control comes to the apartment. He has a whole list of what needs to be checked. If there are flaws in the decoration, technical control does not allow to move on to other work until the builders correct mistakes.
Stage 2. Installation of partitions
At this stage, builders mount new partitions, doorways and niches. The supply department delivers materials and consumables to the apartment. By this time, designers should prepare drawings with new partitions. After the installation of the partitions, a technical control specialist comes to the apartment and checks the work. If everything is fine, they give time to the client to coordinate work and payment.
Photo: all partitions after installation checks technical control
Our client pays only for the work that a specialist in technical control has accepted. Thanks to this approach, it is possible to avoid expensive and difficult to eliminate errors.
Stage 3. Stucked
Then builders begin plastering walls, corners and slopes. The plaster is made both by machine and manually. If the apartment has hidden skirting boards, the supply should be purchased 10 days before plastering.
Photo: plaster can be cement or gypsum
After plastering, a technical control specialist arrives and checks how smoothly the walls are made, whether there are flaws on the surface. Also at this stage the designer is included in the work. He calculates the volume of work that the foreman put up for payment. Next, the plaster checks technical control. If everything is done efficiently, the client coordinates the estimate and pays for it.
Photo: A specialist in technical control checks the corners after plastering walls
The volume of work is double -checked by several specialists so that the estimate for the client is as accurate as possible. After this stage, those pauses flow, usually 3-5 days. At this time, the walls dry evenly.
Photo: plaster gradually dries and gain strength. You can’t open the door and windows in the apartment so that there are no drafts
Stage 4. Black electrician
To start this stage, the buyer acquires all the necessary materials 5 days before the start of work. The client must coordinate and pay all materials.
Photo: Materials accepts the foreman in the apartment
Further, experts conduct an electrician to the points of connection, lighting and sockets. Tech control takes an electrician. The client pays for work.
Photo: an electrician is carried out on the ceiling or floor
Stage 5. Black plumbing
At this stage, not only the purchaser is included in the work, but also the receptor. He purchases built -in plumbing, such as ramps, installations, mixers, 14 days before the start of the stage. Radiators and convectors – 30 days before the start of work. The client also coordinates all the elements before purchasing.
Photo: installation of heating radiators
When everything you need is, specialists begin to work on sewage, water supply and heating.
Photo: Installation and water collector
In addition to technical control, the designer also accepts work. She looks at the location of sockets, switches and plumbing.
Photo: The designer also monitors important elements of the finish
Stage 6.
To start this stage, the designer with the customer must decide on the flooring and on the height of the floor pie. This is necessary so that the floor is in one level throughout the apartment without thresholds and differences. When the flooring is agreed, builders begin to fill the screed. Tech control checks the floor plane (link) and transfers data to the client. After that, the work is coordinated and paid.
Photo: the screed is dried under the film for about 5 days
After this stage, a technopaus sets in, in the interval of which a furnitureman enters the apartment and makes final measurements of space.
It is important to know
- Each stage is checked by a technical control specialist. This approach allows you to avoid complex and expensive errors that will have to be redone for a long time and spend time. Repair is high -quality, fast and without unnecessary costs.
- You pay for each stage separately. This is convenient, because you do not need to save the entire amount for repairs at once, but you can pay it in parts.
- In addition to a technical control specialist, the designer checks the decoration. This gives an additional guarantee that the entire finish will be made exactly the same as it was conceived in a design project.
- The compliance purchases materials after coordination with the client and designer. This approach protects the budget from unnecessary expenses and saves time. We purchase materials precisely in the volume that is needed for repair.
Here you can read about work at the final stage
Write to us on WhatsApp and we will calculate the full cost of repair with work and materials